DavosWorks Brand Services GmbH
2024
Temporary building C3.ai
Wood construction
TU-/GU overall project
Production and assembly
Project management/construction management
Project planning
Project development
An entrance and façade cladding was installed at Promenade 91 as part of the WEF, and a further module was installed above the entrance to the underground car park. The black, matt lacquered wooden cladding was mounted on a terrace grid. The entrance area was framed at the sides and top with an LED rail, which provided indirect lighting. Large LED screens were also integrated into the elements on the left and right. The entire façade cladding was installed within 3 days. The modules were completely prefabricated in Savognin and transported to Davos by truck. The two parts were positioned using a crane and the façade was connected.